Ohio Department of Transportation


Project Specifications:

Location:  Cincinnati, OH

Application: Detention

Product used:  DoubleTrap

Number of pieces: 116 pieces

Number of systems: 1

Total water stored: 63,000 cf

Market: Government/ Community

Project Details: The Ohio Department of Transportation installed a StormTrap detention system at an I-75 off ramp near Cincinnati, OH to reduce the rate of stormwater flowing into the Combined Sewer System.

Challenge: The major challenges of the project was that the site was tight, deep, and located very close to an interstate highway.

Solution:  By installing the StormTrap system, the stormwater flowing rate was reduced. The system fit in a small footprint and 116 units were delivered and installed in three days.

John R. Jurgensen, general contractor of the project stated that “StormTrap system was selected for its small footprint, speed of installation, durability and lower overall project cost”.