Location: North Andover, MA
Application: Infiltration
Product used: 5′-0″ SingleTrap
Number of pieces: 61
Number of units: 1
Total water stored: 31,500 cubic feet
Market: Medical
Project Details: A former ski area was being developed into a senior living community in North Andover, MA and required a stormwater management system to satisfy state and municipal stormwater regulations.
Challenge: The site’s existing conditions presented difficult planning restraints with steep topography and environmental concerns. A large amount of the site development is located within buffer zones to bordering vegetated wetlands and resulted in an increase of impervious surface.
Solution: The StormTrap system was used for stormwater peak flow mitigation and groundwater recharge. “StormTrap provided maximum water storage volume in a limited footprint” stated John Barrows, P.E., project engineer for Marchionda & Associates L.P.